Question: Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students. Activity ID

Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students.

Activity

ID

Immediate Predecessor

Time (Wks)

Design Laptop

A

21

Build Prototype

B

A

5

Evaluate Design

C

A

7

Test Prototype

D

B

2

Write Manual

E

C, D

5

Prep Production

F

C, D

8

Test Production

G

E, F

2

CHaD has recalculated their project scheduling information to include uncertainty into the activity times as indicated below:

Activity

ID

a

m

b

t

v

Design Laptop

A

10

22

28

Build Prototype

B

4

6

14

Evaluate Design

C

4

4

10

Test Prototype

D

1

2

3

Write Manual

E

7

8

9

Prep Production

F

1

5

9

Test Production

G

2

2

2

a) Determine the critical path

ID

ES

EF

LS

LF

TS

CP

A

B

C

D

E

F

G

b) What is the probability the project is completed in 44 weeks or less?

c) What is the probability the project is completed in 38 weeks or less?

Edit: would this work now?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!