Question: Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students. Activity ID
Computer Hardware Development, Inc. (better known as CHaD - also the President and CEOs name) is developing a new laptop computer for students.
| Activity | ID | Immediate Predecessor | Time (Wks) |
| Design Laptop | A | 21 | |
| Build Prototype | B | A | 5 |
| Evaluate Design | C | A | 7 |
| Test Prototype | D | B | 2 |
| Write Manual | E | C, D | 5 |
| Prep Production | F | C, D | 8 |
| Test Production | G | E, F | 2 |
CHaD has recalculated their project scheduling information to include uncertainty into the activity times as indicated below:
| Activity | ID | a | m | b | t | v |
| Design Laptop | A | 10 | 22 | 28 |
|
|
| Build Prototype | B | 4 | 6 | 14 |
|
|
| Evaluate Design | C | 4 | 4 | 10 |
|
|
| Test Prototype | D | 1 | 2 | 3 |
|
|
| Write Manual | E | 7 | 8 | 9 |
|
|
| Prep Production | F | 1 | 5 | 9 |
|
|
| Test Production | G | 2 | 2 | 2 |
|
|
a) Determine the critical path
| ID | ES | EF | LS | LF | TS | CP |
| A |
|
|
|
|
|
|
| B |
|
|
|
|
|
|
| C |
|
|
|
|
|
|
| D |
|
|
|
|
|
|
| E |
|
|
|
|
|
|
| F |
|
|
|
|
|
|
| G |
|
|
|
|
|
|
b) What is the probability the project is completed in 44 weeks or less?
c) What is the probability the project is completed in 38 weeks or less?