Question: Chairs are made in a process with two sequential resources. The processing times for the resources are 0 . 5 0 and 0 . 3

Chairs are made in a process with two sequential resources. The processing times for the resources are 0.50 and 0.38 hours What is the capacity of this process in terms of chairs per hour?