Question: Chairs are made in a process with two sequential resources. The processing times for the resources are 0 . 1 7 and 0 . 1

Chairs are made in a process with two sequential resources. The processing times for the resources are 0.17 and 0.12 hours.
What is the capacity of this process in terms of chairs per hour?
Note: Round your answr to 2 decimal places.
Capacity in terms of chairs per hour