Question: (Chapter 19 Project Management) You are asked to manage a project with 6 activities. The precedence table and activity times are shown below. What is

(Chapter 19 Project Management) You are asked to
(Chapter 19 Project Management) You are asked to
(Chapter 19 Project Management) You are asked to
(Chapter 19 Project Management) You are asked to manage a project with 6 activities. The precedence table and activity times are shown below. What is the slack of activity C? What is the early start time of activity F? If activity A starts in week 6, which of the following statements is TRUE