Question: (Chapter 19 Project Management) You are asked to manage a project with 6 activities. The precedence table and activity times are shown below. If activity

(Chapter 19 Project Management) You are asked to
(Chapter 19 Project Management) You are asked to manage a project with 6 activities. The precedence table and activity times are shown below. If activity A starts in week 6 , which of the following statements is TRUE? The project will be completed as planned since activity A has slack time. Project completion time will be delayed by I week Project completion time will be delayed by 6 weeks. Activity B will have to start in week 7