Question: CHAPTER 3 PROJECT MANAGEMENT 95 the A) 3.9 Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are

CHAPTER 3 PROJECT MANAGEMENT 95 the A) 3.9 Task
CHAPTER 3 PROJECT MANAGEMENT 95 the A) 3.9 Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: ACTIVITY TIME (IN HOURS) 60 IMMEDIATE PREDECESSORS A B 72 5.0 60 A D B, C B, C E 45 7.7 D F G 40 EF a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project completion time? d) Draw a Gantt chart for the project. PX the following table af

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!