Question: 3.9 Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: :) TIME (IN HOURS) IMMEDIATE

3.9 Task time estimates for the modification of

3.9 Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: :) TIME (IN HOURS) IMMEDIATE PREDECESSORS ACTIVITY - A 6.0 B 7.2 5.0 A D 6.0 , E 4.5 B, C F 7.7 D 4.0 G E, F F a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project completion time? d) Draw a Gantt chart for the project. Px a