Question: CHAPTER 3 - PROJECT MANAGEMENT ( CLO 2 ) 6 : 5 : 5 . K N 1 ( 1 ) A network consists of

CHAPTER 3- PROJECT MANAGEMENT (CLO 2)
6:5:5.KN1
(1) A network consists of the activities in the following list. Times are given in weeks.
\table[[Activity,Preceding,Time],[A,--,8],[B,--,3],[C,A,7],[D,A, B,3],[E,C,4],[F,D,9]]
(a) Draw the network diagram.
(b) Calculate the ES, EF, LS, LF, and Slack for each activity.
(c) What is project completion time?
QUESTION 2
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
\table[[Activity,Preceding,\table[[Optimistic],[Time]],\table[[Probable],[Time]],\table[[Pessimistic],[Time]],\table[[Expected],[Time]],Variance],[A,-,7,10,19,,],[B,A,2,2,8,,],[C,A,8,12,16,,],[D,A,3,5,10,,],[E,B,4,6,8,,],[F,B,6,8,10,,],[G,C,F,2,3,4,,],[H,D,2,2,8,,],[I,H,6,8,16,,],[J,G,I,4,6,14,,],[K,E,J,2,5,8,,]]
(a) Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above.
(b) Which activities form the critical path?
(c) What is the estimated time of the critical path?
(d) What are the project variance and the project standard deviation?
(e) What is the probability of completion of the project before week 42?
CHAPTER 5: DESIGN OF GOODS & SERVICES (CLO2)
QUESTION 1
A. Briefly explain how product life-cycle management (PLM) impacts product design.
B. Answer Question 15 of the B. END-OF-CHAPTER ProbLEMS
5.15
QUESTION 2:
Video CASE STUdies
1 PRODUCT DESIGN AT NAUTIQUE BOAT COMPANY
A 7-minute video, filmed specifically for our text, is available online.
1.
2.
3.
4.
 CHAPTER 3- PROJECT MANAGEMENT (CLO 2) 6:5:5.KN1 (1) A network consists

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!