Question: Homework Assignment for Chapter 3 Project Management 1. [2 pts) Construct a Gantt chart for activities through the project described by the following set of

Homework Assignment for Chapter 3 Project
Homework Assignment for Chapter 3 Project Management 1. [2 pts) Construct a Gantt chart for activities through the project described by the following set of activities. Activity Immediate Predecessor(s) Time (weeks) A 3 7 2 B E F G B B D E AN COWO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 weeks. (Enter your [2 pts) The project completion time of the above project is response as a whole number.) stall the fall table the antidine with the grann und Page 1 of 5 1 of 731 words TX Focus w A MacBook Pro CER e