Question: (Chapter 4: Process Improvement) Consider a process consisting of three resources. The process activities are always performed in the following sequence. Resource 1 has a
(Chapter 4: Process Improvement) Consider a process consisting of three resources. The process activities are always performed in the following sequence. Resource 1 has a processing time of 5 minutes per unit. Resource 2 has a processing time of 4 minutes per unit. Resource 3 has a processing time of 6 minutes per unit. Resource 1 is staffed by worker A and A's wage rate is $13 per hour. Resource 2 is staffed by worker B and B's wage rate is $13 per hour. Resource 3 is staffed by worker C and C's wage rate is $20 per hour. Assume the demand rate is 8 units/hour. There is unlimited space for buffer inventory between the resources.
What is the approximate average labor utilization? Group of answer choices 33% 77% 59% 67 %