Question: Chapter 4: Project Management (CPM & PERT TECHNIQUES) QUESTION 1 A network consists of the following list. Times are given in weeks. Preceding Activity A

Chapter 4: Project Management (CPM & PERT

Chapter 4: Project Management (CPM & PERT

Chapter 4: Project Management (CPM & PERT TECHNIQUES) QUESTION 1 A network consists of the following list. Times are given in weeks. Preceding Activity A B C D E F G H I J K Duration 9 2 12 5 6 A A A B B CF t D H GI E, ] 3 2 8 6 2 a. Draw the network diagram. b. Which activities form the critical path? c. What is the duration of the project completion? QUESTION 2 A PERT problem is detailed in the table below. Times are given in weeks. Preceding Activity A B D E F G H I J K A A A B B CF D H GI E,J Optimistic Time 7 2 8 3 4 6 2 2 6 4 2 Probable Time/ Most likely time 9 2 12 5 6 8 3 2 8 6 2 Pessimistic Time 14 8 16 10 8 10 4 8 16 14 5 a. Calculate the expected time and ES, EF, LF, and LS of each activity. b. Draw diagram network for this project. c. What are the project variance and the project standard deviation? d. What is the estimated completion time? e. What is the probability of completion of the project after week 40

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!