Question: Chapter 5 Basis of Estimate In-Class Exercise Complete the BOE form below to develop an estimate for ONE of the tasks shown below: Prepare a

Chapter 5 Basis of Estimate In-Class Exercise

  • Complete the BOE form below to develop an estimate for ONE of the tasks shown below:
  1. Prepare a soccer field for play
  2. Paint the interior of a 2,000 sq foot house with 9 rooms (existing structure)
  3. Install drywall to the interior of a 2,000 sq foot house (new construction)
  4. Install landscaping on a 10,000 sq foot lot, to include irrigation, topsoil, plants, and sod
  5. Build a fence surrounding a 10,000 sq foot lot, including installation of 2 gates
  • You wont be graded on the accuracy of your estimate, so dont worry about getting an exact estimate of dollars or hours/units. This exercise is intended for you to practice the estimating process.
  • Remember that the Scope Statement defines what is in your estimate and the assumptions define what is out of your estimate.

Name:

Task Name:

Task Duration (in days):

Detailed Scope Statement (Define the scope to be accomplished):

Assumptions:

Labor Estimate

Resource Description

Estimated Hours

Estimated Cost/Hour

Total Estimated Cost for Labor

Non-Labor Estimate

Resource Description

Estimated Units

Estimated Cost/Unit

Total Estimated Cost for Non-Labor

Total Estimate

$

Rationale for Estimate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!