Question: ( Chapter 6 ) : Estimate the production rate in b f h r of the entire process of loading, unloading and hauling lumber on
Chapter : Estimate the production rate in of the
entire process of loading, unloading and hauling lumber
on a construction site. The lumber will be hauled miles
at an average haul speed of miles per hour. The
average return speed will be miles per hour. A crew of
three laborers and one truck driver will be able to unload
and stack the lumber at bf per hour per worker. A
loader will load the trucks at the stockpile in minutes.
The capacity of the truck is board feet. Points
You have to calculate the inefficiency of a laborer for a
task. Assume the following per day.
a Determine the # of hours you must carry per shift
for each laborer
Assume:
Safety meeting minutes
Two Breaks minutes
Lunch minutes
hour shift
b With the information above a Determine the #
of hours you must carry per shift for each laborer
with a efficiency:
Assume:
Inefficiency factor
Step by Step Solution
There are 3 Steps involved in it