Question: Chapter 6 Exercise Name: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Using the following information,
Chapter Exercise
Name:
Using the following information, develop an AON project network. Complete the forward and
backward pass, compute the activity slack, and identify the critical path. Answer the following
questions:
What is the critical path?
How many weeks to complete?
What is the slack for activity C For activity F
Activity Predecessor Time Weeks
A None
B A
C A
D B
E C D
F D
G E F
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock