Question: Chapter 6 Question 1 Page 291 An assembly line with 17 tasks is to be balanced The longest task i5 2.4 minutes, and the tobaf
Chapter 6 Question 1 Page 291 An assembly line with 17 tasks is to be balanced The longest task i5 2.4 minutes, and the tobaf time for all tasks is 18 minutes. The line will operate for 450 minutes per day A. What is the minimum and maximum cycle times? Minimurt Maximum B. What ranpe of output is theorhetically possible for the line? Minimum Units and Maximum Units C. What is the minimum number of workstations needed if the Maximum output is to be soughi? D. What cycke time will provide an output rate of 125 units per day? E What outgat poterisal will resuit if the cycle tome is 9 minutes or 12 munutes