Question: Chapter Three Part One Problems Question #1 - /18 marks A network consists of the activities in the following list. Times are given in weeks.
Chapter Three Part One Problems
Question #1 - /18 marks
A network consists of the activities in the following list. Times are given in weeks.
Activity
Preceding
Duration
A
--
8
B
--
3
C
A
7
D
A, B
3
E
C
4
F
D
6
a. Draw the AON network diagram. (3 marks for attempting the diagram, 1 mark for correct diagram)
b. Calculate the ES, EF, LS, LF, and Slack for each activity. (6 marks for showing calculations for each, 4 marks for correct answers)
c. What is project completion time? (3 marks for showing calculations, 1 mark for correct answer)
Question #2 - /18 marks
Draw the AOA (3 marks for attempting diagram, 1 mark for correct diagram) and AON (3 marks for attempting diagram, 1 mark for correct diagram) networks for the following project and calculate the minimum project duration (6 marks for showing calculations for each, 4 marks for correct answers).
Activity
Duration
(days)
Immediate
Predecessors
A
10
---
B
8
---
C
2
A
D
4
A
E
5
B, C, D