Question: Chart 1 TASK DURATION PREDECESSOR SUCCESSOR A 2 C B 1 D,E C 4 A F D 2 B I E 4 B G,H F

Chart 1

TASK

DURATION

PREDECESSOR

SUCCESSOR

A

2

C

B

1

D,E

C

4

A

F

D

2

B

I

E

4

B

G,H

F

1

C

I

G

3

E

I

H

1

E

J

I

3

D,F,G

J

J

2

I,H

Project 1

You are the PM for Project Bravo Sierra, a project with 10 activities (Tasks). The durations (time to complete each task), and predecessors and successors are identified in the table below. Tasks A and B

Build a PERT chart based on the information in Chart 1.

  1. How many days of work are required to complete the project? __________________
  2. Assuming you have the workers needed, how quickly can the job be accomplished? __________

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!