Question: Chart 1 TASK DURATION PREDECESSOR SUCCESSOR A 2 C B 1 D,E C 4 A F D 2 B I E 4 B G,H F
| Chart 1 | |||
| TASK | DURATION | PREDECESSOR | SUCCESSOR |
| A | 2 |
| C |
| B | 1 |
| D,E |
| C | 4 | A | F |
| D | 2 | B | I |
| E | 4 | B | G,H |
| F | 1 | C | I |
| G | 3 | E | I |
| H | 1 | E | J |
| I | 3 | D,F,G | J |
| J | 2 | I,H |
|
Project 1
You are the PM for Project Bravo Sierra, a project with 10 activities (Tasks). The durations (time to complete each task), and predecessors and successors are identified in the table below. Tasks A and B
Build a PERT chart based on the information in Chart 1.
- How many days of work are required to complete the project? __________________
- Assuming you have the workers needed, how quickly can the job be accomplished? __________