Question: Check my work Problem 12-9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for

Check my work Problem 12-9 Assume that you are the manager of a shop that assembles power tools. You have just received an order for 52 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws is Item Saw A B D E E Lead Time (weeks) 2 1 2 2 1 1 2 On Hand 15 10 5 65 20 Components A(2), B(1), C(4) E (3), D(1) D(2), F(3) E (2), D (2) Develop the material requirements plan for component Eusing lot-for-lot ordering. (Leave no cells blank - be certain to enter "O" wherever required.) 3 Item: E(3) 6 E (2) LT - 1 wk. Beg. Inv. Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Nout