Question: choice questions each is worth 1 . 5 points, and two long problems ( 4 . 5 points ) . But your grade will be

choice questions each is worth 1.5 points, and two long problems (4.5 points). But your grade will be considered out of 120
Question 76
1.5pts
Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done-
In the next project phase
Throughout all project phases
For successful completion of the current project phase
For successful completion of the current and subsequent project phases