Question: ( Choose the best answer ) This activity involves regularly gathering data on project performance, comparing actual performance to planned performance, and taking corrective actions

(Choose the best answer) This activity involves regularly gathering data on project performance, comparing actual performance to planned performance, and taking corrective actions if actual performance is behind planned performance
Question 4 options:
Closing
Controlling
Initiating
Planning