Question: Circular blanks are loaded into a deep drawing machine by an automatic loading and unloading mechanism. The loading and unloading task takes 2 0 sec
Step by Step Solution
There are 3 Steps involved in it
a Time to complete the batch Cycle time per part Loadingunloading time per cycle 20 seconds Drawing time per cycle 10 seconds Total cycle time per part Loading time Drawing time 20 sec 10 sec 30 secon... View full answer