Question: Clark Construction is building a set of new condominiums in the Virginia Beach. The project consists of eighteen buildings, each housing twelve condominiums. Each building
Clark Construction is building a set of new condominiums in the Virginia Beach. The project
consists of eighteen buildings, each housing twelve condominiums. Each building will border the
Virginia Beach Golf Course designed by J M Architects. The minimum price for a condominium unit
is $ and buyers expect a highquality project. Response to the initial promotion was so great
that CLARK Construction presold all units based solely on an architects conception and
schematic plans of the project. One reason for the quick sellout may have been the YOU CAN MOVE
IN BY OCTOBER campaign. As part of this campaign, CLARK promised rebates of $ cash
to all buyers if all the facilities, buildings, and other amenities were not completed by October
As of midJanuary, the project is well underway. The following PERTCPM network details the
precedence for the activities of the tasks remaining to be completed in the project. R and T will be
subcontracted.
Threetime estimates in days for each of the other activities needed for each condo have been
determined and are given in the following table Note: all the condos will be constructed concurrently
You are required to use a full day as the smallest unit for scheduling the activities:
Activity R the underground sewer activity, consists of installing pipes and connections to join
all eighteen buildings to the main city sewer system. CLARK Construction selected the Comey
Construction alternative for this activity.
Comey Construction has submitted a bid of $ for the design and construction of the
required sewer project. It estimates a most likely completion time of days, with a difference of
plus or minus three days for the optimistic and pessimistic time estimates.
Activity T the stream building activity, involves building a stream that runs throughout the project
and connects the western and eastern boundaries. CLARK has selected the Lakeport Inc. alter
native:
CLARK has received a bid of $ from Lakeport, Inc. to design and build a meandering
stream that will most likely be finished in days, give or take five days.
Each activity is estimated to need people with a cost of $day per person. The indirect cost
of the project is estimated to be $day Assume that today is January and that all the work
is to be done on a fivedayperweek basis including holiday periods. Prepare a report for this
project within which you address the followings:
DDevelop a budget for the project based on your recommended plan. And provide any
financial analysis you can provide.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock