Question: -class EV Practice Name: ID: 1) You have a project to install 100 solar panels on a roof. You estimate that you can install 10


-class EV Practice Name: ID: 1) You have a project to install 100 solar panels on a roof. You estimate that you can install 10 panels a day, and thus it will take you 10 working days. The cost per installed solar panel, including material and labour is $2,250. You are at the end of Day 6, at 4pm and realize you have installed 55 panels and the cost is $152,000 a. What is the total cost of the project? What percent of the work has been done? b. What is the planned value, earned value, actual cost, at day 6 for cost and Schedule? EV PV AC Cost Schedule -2001 c. What is the cost variance and schedule variance? What is the CPI and SPI? What is the status of the budget and schedule? IM MGMT 8630 IN-class EV Practice Name: ID: 1) You have a project to install 100 solar panels on a roof. You estimate that you can install 10 panels a day, and thus it will take you 10 working days. The cost per installed solar panel, including material and labour is $2,250. You are at the end of Day 6, at 4pm and realize you have installed 55 panels and the cost is $152,000 a. What is the total cost of the project? What percent of the work has been done? b. What is the planned value, earned value, actual cost, at day 6 for cost and Schedule? EV PV AC Cost Schedule C. What is the cost variance and schedule variance? d. What is the CPI and SPI? What is the status of the budget and schedule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock