Question: Class Exercise #3 3) What is the estimated expected (mean) time for project completion? A. 22 days B. 72 days C. 100 days D. 120

 Class Exercise \#3 3) What is the estimated expected (mean) time

Class Exercise \#3 3) What is the estimated expected (mean) time for project completion? A. 22 days B. 72 days C. 100 days D. 120 days E. 221 days