The following table contains information about a project. Use it to answer the problems 33 - 34:
The Project Manager is about to begin a project comprised of the following six activities:
Time Estimnates ( Days)
| Activity | Precedes | Optimistic | Most Likely | Pessimistic |
| Start | A,B,C | |||
| A | D | 38 | 50 | 62 |
| B | E | 90 | 99 | 108 |
| C | End | 85 | 100 | 115 |
| D | F | 19 | 25 | 31 |
| E | End | 91 | 100 | 115 |
| F | End | 62 | 65 | 68 |
31. What is the estimated expected (mean) time for project completion?
| A. | 200 days | |
| B. | 199 days | |
| C. | 100 days | |
| D. | 140 days | |
| E. | 440 days |
32. What is the probability that the critical path for this project will be completed within 210 days?
| A. | 0.9987 | |
| B. | 0.9544 | |
| C. | 0.9772 | |
| D. | 0.8413 | |
| E. | 0.6826 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock