Question: The following table contains information about a project. Use it to answer the problems 33 - 34: The Project Manager is about to begin a

The following table contains information about a project. Use it to answer the problems 33 - 34:

The Project Manager is about to begin a project comprised of the following six activities:

Time Estimnates ( Days)

Activity Precedes Optimistic Most Likely Pessimistic
Start A,B,C
A D 38 50 62
B E 90 99 108
C End 85 100 115
D F 19 25 31
E End 91 100 115
F End 62 65 68

31. What is the estimated expected (mean) time for project completion?

A.

200 days

B.

199 days

C.

100 days

D.

140 days

E.

440 days

32. What is the probability that the critical path for this project will be completed within 210 days?

A.

0.9987

B.

0.9544

C.

0.9772

D.

0.8413

E.

0.6826

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!