Question: Class name: Operations and Supply Chain Management Question 1: A network consists of the activities in the following list. Times are given in weeks. Activity

Class name: Operations and Supply Chain Management
Class name: Operations and Supply Chain
Question 1: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding A -- B -- A D A , B FD Time 8 3 7 3 4 a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. Task Early Early Late Late Slack Start Finish Start Finish B C D E F c. What is project completion time