Question: Class Task 1. Construct a network diagram which satisfies the following relationships: A, B and C are the first activities of the project and can

Class Task 1. Construct a network diagram which satisfies the following relationships: A, B and C are the first activities of the project and can start simultaneously. A and B precede D. B precedes E,F and H. F and C precede G. E and H precede I and J. C,D,F and J precede K. K precedes L. I, G and L are the terminal activities of the project