Question: Clients are the flow unit in a process with two sequential resources. The capacities of the resources are 1.2 and 1.3 clients per minute. Demand

 Clients are the flow unit in a process with two sequential

Clients are the flow unit in a process with two sequential resources. The capacities of the resources are 1.2 and 1.3 clients per minute. Demand occurs at the rate 1.7 clients per minute. What is the utilization (\%) of the second resource? Note: Round your answer to 1 decimal place