Question: Clients are the flow unit in a process with two sequential resources. The capacities of the resources are 1.2 and 1.3 clients per minute. Demand
Clients are the flow unit in a process with two sequential resources. The capacities of the resources are 1.2 and 1.3 clients per minute. Demand occurs at the rate 1.7 clients per minute. What is the utilization (\%) of the second resource? Note: Round your answer to 1 decimal place
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts