Question: Customers are the flow unit in a process with two sequential resources. The capacities of the resources are 41 and 60 customers per minute.
Customers are the flow unit in a process with two sequential resources. The capacities of the resources are 41 and 60 customers per minute. Demand occurs at the rate 44 customers per minute. What is the utilization (%) of the second resource? Note: Round your answer to 1 decimal place. Utilization %
Step by Step Solution
There are 3 Steps involved in it
Utilization is calculated by dividing the actual flow rate ... View full answer