Question: ( CLO: 2 , CLO: 4 , CLO: 6 ) ) Consider the following project problem with detailed information in the table below. Times are
CLO: CLO: CLO: Consider the following project problem with detailed information in the table below. Times are given in weeks.
Activity
Immediate
Predecessors
Optimistic
Time
Most Likely
Time
Pessimistic
Time
A
B
A
C
B
D
A
E
B
F
B
G
C F
H
D
I
H
J
G I
K
E J
a Calculate the expected duration D and variance of the following activities.
Activity
D
Variance
B
Answer Question
Answer Question
E
Answer Question
Answer Question
K
Answer Question
Answer Question
b Which activities form the critical path? NB: The answer to this question should be written in the following format: ABCDEF, no space between letters
Answer Question
c What is the estimated time of the critical path?
Answer Question
weeks
d If the project is due to be completed in weeks, what is the probability that the project will be completed on the due date?
Answer Question
e If the project manager wants at least a probability that the project will be completed on the due date, what is the shortest project due date that will satisfy the manager?
Answer Question
weeks
f How many weeks can you delay activity F without impacting the expected project completion date?
Answer Question
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
