Question: CLO # 7 : Develop a Preliminary ( conceptual ) Schedule for a Commercial Building Match the correct answers for the difference between Total Float
CLO #: Develop a Preliminary conceptual Schedule for a Commercial Building
Match the correct answers for the difference between Total Float vs Free Float vs Independent Float.
Impact on Project Completion Date
Maximum amount of time that the activity can be
delayed without delaying the completion time of the
project.
maximum amount of time that the activity can be
delayed without delaying the early start of any of its
successors, assuming its predecessors were
completed early
maximum amount of time that the activity can be
delayed without delaying the early start of any of its
successors, assuming its predecessors were
completed late.
Choose
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock