Question: Closing the loop in an MRP system refers to using CRP to check the validity of the Master Production Schedule. a. False b. True If

"Closing the loop" in an MRP system refers to"Closing the loop" in an MRP system refers to"Closing the loop" in an MRP system refers to

"Closing the loop" in an MRP system refers to using CRP to check the validity of the Master Production Schedule. a. False b. True If a part is not needed in a certain period in which it is scheduled to be done, the part should be de- expedited to reflect its actual need date. a. True O b. False The quantity of a planned order release for a part equals the net requirements for the part. a. True O b. False