Question: CMTT-2130 Construction Scheduling Week 8 Assignment #1 Directions: Write the following schedule out on paper and complete the ES, EF, LS, LF & TF for
CMTT-2130 Construction Scheduling
Week 8 Assignment #1
Directions: Write the following schedule out on paper and complete the ES, EF, LS, LF & TF for each activity. When complete and you have the calculations done then create a PDF or Pic of your work and upload it into the correct folder in BlackBoard. Then you will enter the same information into the P6 Primavera Software and complete the schedule as you have been doing. When complete then Export the file and upload into its correct folder in BlackBoard.
Once you have received the 10 Notice to Proceed (Start Milestone) then you can begin the 20 Prep the Slab (4). After the slab has been prepped for concrete you can then pour the 30 Slab-On-Grade (2). After the SOG is completed you can start the 40 Temporary Power (3) which precedes the 50 Rough Framing (10). The 60 Exterior Finish (10) will begin after the rough framing is completed as will the 70 Interior Finish (12) except it will have a Start to Start relationship with a 4 day lag. The 80 Landscape (3) will follow the exterior finish. The 90 Punch List (5) will start as soon as the landscaping and interior finish is complete.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts