Question: We produce finished product A, using components Q, R and S, and raw materials X and Y, as shown in the following Bill of Materials
We produce finished product A, using components Q, R and S, and raw materials X and Y, as shown in the following Bill of Materials (BOM):
The Master Production Schedule (MPS) shows the plan is to begin production of A in the following quantity each week:
Week:
1
2
3
4
5
6
7
8
MPS
55
35
25
40
80
45
65
30
Use this information to answer all of the questions on this page.
1-1. The scheduled receipt for item Q is 120 on week 1, as shown below. Fill in the appropriate gross requirements for Q based on the BOM and the MPS of product A shown above, and complete the remaining MRP table.
Item Q
On Hand:
90
LT =
1 week
Safety Stock:
10
Lotsize:
POQ = 2 weeks
Week:
1
2
3
4
5
6
7
8
Gross Requirements
Scheduled Receipts
120
Projected On Hand
Net Requirement
Planned Receipt
Planned Release
Continued on next page
1-2. The scheduled receipt for item X is 450 on week 1, which is 20 less than the fixed order quantity (FOQ) of 650, as shown below. Fill in the appropriate gross requirements for X based on the BOM shown above and the MRP table of item Q you've worked in the previous problem, and complete the remaining MRP table.
Item X
On Hand:
165
LT =
2 week
Safety Stock:
150
Lotsize:
FOQ =
650
Week:
1
2
3
4
5
6
7
8
Gross Requirements
Scheduled Receipts
450
Projected On Hand
Net Requirement
Planned Receipt
Planned Release
2. Find the ES, EF, LS, LF, and slack time for each activity in the project shown below:
Activity
Immediate Predecessors
Duration
A
-----
5
B
A
6
C
A
3
D
B
3
E
B, C
4
F
C
4
G
D, E, F
3
Activity
ES
EF
LS
LF
Slack
A
B
C
D
E
F
G