Question: Cnapter 8 . Assigmmemit Balance the assembly line shown below for ( a ) a shift output of 5 0 pieces and ( b )

Cnapter 8. Assigmmemit
Balance the assembly line shown below for (a) a shift output of 50 pieces and (b) a shift output of 30 pleces. Assume an five-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case.
a. Fill in the table below for a shift output of 50 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
\table[[Workstation,Tasks,Total Time],[1,- Select-,],[2,,],[3,,],[4,- Select-0,]]
Idle Time
What is the assembly-line efficiency? Round your answer to one decimal place.
What is the assembly-line efficiency? Round your answer to one decimal place.
%
Fill in the table below for a shift output of 30 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
\table[[Workstation,Tasks,Total Time],[1,,],[2,,],[3,-Select--,],[,Total,]]
Idle Time
What is the assembly-line efficiency? Round your answer to one decimal place.
%
 Cnapter 8. Assigmmemit Balance the assembly line shown below for (a)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!