Question: Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.


\begin{tabular}{|c|c|c|c|} \hline Activity & Description & ImmediatePredecessor & Time(weeks) \\ \hline A & Survey building site & & 5 \\ \hline B & Develop initial design & & 7 \\ \hline C & Obtain board approval & A, B & 10 \\ \hline D & Select architect & C & 3 \\ \hline E & Establish budget & C & 6 \\ \hline F & Finalize design & D, E & 14 \\ \hline G & Obtain financing & E & 12 \\ \hline H & Hire contractor & F, G & 8 \\ \hline \end{tabular} (c) Develop the activity schedule for the project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts