An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.
Which two of the following items should be included in the planning? Choose two
Daily scrum
Sprint retrospective
Sprint backlog
Increments
Sprint review