Question: Comment on the critical ratio for task D. Progress Cost Activity Actual Schedule Budget Actual CR A 30 40 220 330 0.50 B 200 205

Comment on the critical ratio for task D.

Comment on the critical ratio for task D. Progress Cost Activity Actual Schedule Budget Actual CR A 30 40 220 330 0.50 B 200 205 5000 4900 1.00 550 500 450 500 0.99 D 200 160 600 520 1.44 Doing well, do not notify anyone Ignore, critical ratio means nothing for this task Monitor, notify management only if status changes Off track, notify management O Nothing, on budget and on schedule