Question: Comment on the critical ratio for task D Comment on the critical ratio for task D. Progress Cost Activity Actual Schedule Budget Actual A 30
Comment on the critical ratio for task D
Comment on the critical ratio for task D. Progress Cost Activity Actual Schedule Budget Actual A 30 40 220 330 200 205 5000 4900 C 550 500 450 500 D 200 160 600 520. O Doing well, do not notify anyone Ignore, critical ratio means nothing for this task O Monitor, notify management only if status changes O Off track, notify management O Nothing, on budget and on schedule Ps B CR 0.50 1.00 0.99 1.44