Question: Company ABC is doing a pipeline construction project. For simplicity sake, let's assume that five risks were identified for this project which will have impact
Company ABC is doing a pipeline construction project. For simplicity sake, let's assume
that five risks were identified for this project which will have impact of the cost. Probability of
happening of each of the risk is I understand an event with probability of
happening, does not qualify as risk, but let's ignore this fact for this exercise But there is no
certainty around the cost impact of risks. Following Table shows the range of cost impacts of the
risks based on the expert opinion.
You want to decide contingency for the project based on the costs impacts of these risks. Assume
that these risks are only source of uncertainty in the project and no other risks exist in the
project.
Build a Monte Carlo Simulation model in the excel sheet to calculate the contingency for the
project. Use @Risk software to perform the probabilistic analysis. Model should be formulated
with the aim to answer the following questions.
How much contingency you will recommend for the project so that you confident
that contingency will be enough to cover the cost impacts of above listed risks
How much contingency you will recommend for the project so that you confident
that contingency will be enough to cover the cost impacts of above listed risks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
