Company C is interested in using rates at capacity to better understand its costs of unused capacity.
Fantastic news! We've Found the answer you've been seeking!
Question:
Company C is interested in using rates at capacity to better understand its costs of unused capacity. It expects to pay 146,000 in wages this year. In recent years, wages have ranged from a low of 82,000 to a high of 189,000 while the average was 120,000. Overhead costs have been largely fixed at 948,000 in recent years. What is the expected cost of unused capacity this year?