Company reported the following information related to Job 101. Job 101 Units 500 Direct materials $10,000 Direct
Fantastic news! We've Found the answer you've been seeking!
Question:
Company reported the following information related to Job 101.
Job 101 | |
Units | 500 |
Direct materials | $10,000 |
Direct labor | $2,000 |
Direct labor hours | 100 |
Overhead is applied at rate of $10 per direct labor hour.
Quality inspection showed 10 of the 500 units were defective. The units had to be reworked requiring additional direct materials of $140 and direct labor of $60 (3 hours). The rework is considered normal spoilage.
Determine the total cost of Job 101.