Question: Comparing actual cost variance across projects uses an index rather than dollar amount, because ________. Monetary variance does not include foreign currency Variances in schedule

Comparing actual cost variance across projects uses an index rather than dollar amount, because ________. Monetary variance does not include foreign currency Variances in schedule are not included Dollar variance is relative to the size of the project Current interest rates are not included in monetary value