Question: Comparing target schedule dates with the actual or forecasted start and finish dates is an example of: Select one: a. Progress reporting. b. Conducting a
Comparing target schedule dates with the actual or forecasted start and finish dates is an example of:
Select one:
a. Progress reporting.
b. Conducting a variance analysis.
c. Using project management software.
d. Calculating a cost performance index (CPI) value.
Using the weighted duration average of an activity based on the worst-case scenario, best-case scenario and most likely estimates means using:
Select one:
a. Bottom-up estimating.
b. Three-point estimates.
c. Analogous estimating.
d. Parametric estimating.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
