Question: Comparing target schedule dates with the actual or forecasted start and finish dates is an example of: Select one: a. Calculating a cost performance index
Comparing target schedule dates with the actual or forecasted start and finish dates is an example of: Select one: a. Calculating a cost performance index (CPI) value. b. Conducting a variance analysis. c. Using project management software. d. Progress reporting