Question: Complete a critical path analysis to answer the following: What is the latest start for activity 5 ? Activity ID Description Activity Predecessor Activity Time

Complete a critical path analysis to answer the following:
What is the latest start for activity 5?
Activity
ID
Description
Activity
Predecessor
Activity
Time (weeks)
1
Staff
None
2
2
Develop market program
1
3
3
Select channels of distribution
1
8
4
Patent
1
10
5
Pilot production
1
4
6
Test market
5
4
7
Ad promotion
2
4
8
Set up for production
4,6
16