Question: Complete the CPM illustrated below. Completed the forward pass, and backward pass, calculate the project duration, total floats, and the critical path activities ( if

Complete the CPM illustrated below. Completed the forward pass, and backward pass, calculate the project duration, total floats, and the critical path activities (if any).
\table[[,,,\table[[Task Duration],[Thours)]]],[A ID,Task Description,Task Predecessors,],[Project start,,0,],[B,Buy materials for A,A,10],[C,Buy materials for B,A,20],[D,Build A,B, C,30],[E,Build B,B, C,20],[F,Polish and finish B,E,40],[G,Join A and B,D, F,20],[H,Project finish,G,0]]