Question: Complete the DRP records for periods 2 through 4 below, using the error Addback Method to update the records based on actual demand. -Leave blank

Complete the DRP records for periods 2 through 4 below, using the error Addback Method to update the records based on actual demand.

-Leave blank if no entry is needed.

-As new periods enter the planning horizon, assume a forecast of 30 units in Periods 6, 7, and 8.

-Must show all calculations in the cells below to receive full credit.

Period
On hand 1 2 3 4 5
Forecast Requirements 30 30 30 30 30
In Transit 60
Projected Available Balance 10 40 10 40 10 40
Planned Shipments 60 60

Ship Qty= 60, Lead Time = 1; Safety Stock:10

Period 1 Actual Demand: 24

Cumulative Error
Period
On hand 2 3 4 5 6
Forecast Requirements
In Transit
Projected Available Balance
Planned Shipments

Ship Qty=60; Lead Time=1; Safety Stock=10

Period 2 Actual Demand: 38

Cumulative Error
Period
On hand 3 4 5 6 7
Forecast Requirements
In Transit
Projected Available Balance
Planned Shipments

Ship Qty=60; Lead Time=1; Safety Stock=10

Period 3 Actual Demand: 27

Cumulative Error
Period
On hand 4 5 6 7 8
Forecast Requirements
In Transit
Projected Available Balance
Planned Shipments

Ship Qty=60; Lead Time=1; Safety Stock=10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!