Question: Complete the following problem using the critical path method. Activity Immediate Predecessor Time (days) A 2 B A 4 C F 5 F B, L
Complete the following problem using the critical path method.
| Activity | Immediate Predecessor | Time (days) |
| A |
| 2 |
| B | A | 4 |
| C | F | 5 |
| F | B, L | 8 |
| G | K, M | 3 |
| K | B | 1 |
| L | A | 5 |
| M | B | 2 |
| T | F | 4 |
| V | C, G, T | 7 |
-Given the project activity information above, draw the project network diagram using the activityon-node (AON) style.
- On the network, show all COM network values (i.e., ES, EF, LS, LF, slack).
- What is the critical path (also remember to clearly show it on your network diagram.).
- What is the total project completion time?