Question: Complete the following problem using the critical path method. Activity Immediate Predecessor Time (days) A 2 B A 4 C F 5 F B, L

Complete the following problem using the critical path method.

Activity

Immediate Predecessor

Time (days)

A

2

B

A

4

C

F

5

F

B, L

8

G

K, M

3

K

B

1

L

A

5

M

B

2

T

F

4

V

C, G, T

7

-Given the project activity information above, draw the project network diagram using the activityon-node (AON) style.

- On the network, show all COM network values (i.e., ES, EF, LS, LF, slack).

- What is the critical path (also remember to clearly show it on your network diagram.).

- What is the total project completion time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!