Question: Complete the following table. Lead time for the part is 2 weeks. The lot size is 50. In what periods should the order be released,

Complete the following table. Lead time for the

Complete the following table. Lead time for the part is 2 weeks. The lot size is 50. In what periods should the order be released, and what should be the size of those orders. Please explain. 0 1 2 3 4 5 6 7 20 30 50 50 20 30 10 70 Gross Requirements Project Available Net Requirements Planned Order Receipt Planned Order Release